Nobody enjoys estimating a software project. Developers know they're guessing, and clients know the number will probably move. It gets done anyway, because a business needs a budget to plan against - the goal is just making the guess honest instead of optimistic.
Honesty about a slipping date costs a difficult conversation early. Silence about it costs trust later.
The mistake that breaks every timeline
The most common failure is estimating the best case: the API behaves exactly as documented, the design doesn't change once it's approved, and nobody on the team gets pulled onto something else for a week. None of that is realistic, and a timeline built on it is wrong before the project even starts. The more useful habit is planning for the friction that actually shows up - because it always does - rather than pretending it won't this time.
Break it down until it's actually estimable
A feature that takes longer than three days to build is too large a unit to estimate accurately - it's really several smaller decisions bundled together, each with its own uncertainty. Splitting it down into pieces that small forces the genuinely hard parts to surface early, while they're still cheap to discuss, instead of six weeks in when they're expensive to discover.
Communicate the slip on day two, not on the deadline
If a third-party integration is running behind, the useful moment to say so is the day it becomes clear, not the day the deadline arrives and the delay can no longer be hidden. Honesty about a slipping date costs a difficult conversation early. Silence about it costs trust later, and trust is the more expensive thing to rebuild.